title: Harbor Bridge Program
page:
size: A4 landscape
margin: 14mm 16mm 16mm
header:
left: "🌉 **{title}** · weekly status"
right: "✅ 4 on track · ⚠️ 1 at risk · ⛔ 0 blocked"
footer:
left: "*Program office*"
center: ""
right: Page {page} of {pages}
---
# Harbor Bridge Program: week 14
The page is turned with one word, `size: A4 landscape`, so the wide schedule and the status table read without wrapping.
```mermaid
gantt
title Refurbishment schedule, 2026
dateFormat YYYY-MM-DD
axisFormat %b %d
section Design
Structural survey :done, d1, 2026-02-02, 15d
Detailed design :done, d2, after d1, 20d
section Permits
Navigation authority :done, p1, 2026-02-16, 25d
Heritage consent :active, p2, 2026-03-02, 30d
section Works
Scaffold and containment : w1, 2026-04-01, 10d
Blast and repaint, span 1 :crit, w2, after w1, 25d
Bearing replacement :crit, w3, after w2, 12d
Deck resurfacing : w4, after w3, 8d
```
| Workstream | Owner | Status | This week | Next week |
|:--|:--|:--|:--|:--|
| Design | Ana Rusu | ✅ Done | Drawings issued for construction | Close out comments |
| Permits | Ion Ceban | ⚠️ At risk | Heritage board asked for a paint sample | Submit sample on Tuesday |
| Scaffold | Maria Lungu | ✅ On track | Containment rig delivered | Start erection on span 1 |
| Repaint | Victor Popa | ✅ On track | Paint batch tested, adhesion 9.2 MPa | Blast trial area |
| Traffic | Elena Gheorghe | ✅ On track | Diversion signs agreed with the city | Publish notice |
> [!WARNING]
> Heritage consent is the critical path. A two-week delay moves the bearing replacement into the summer closure window.